UPDATE on UNISON response to Parking being outsourced to NSL

urgent update

Yesterday all the contractors were formally told who had won the contraxct.

The Council is now in what is known as the Alacatel period

When does the Standstill Period commence?

The period kicks in from the date the authority decides to award the contract. Usually this will come towards the end of an often lengthy procurement process where bidders will have been shortlisted and finally whittled down to one, for example through a process called “competitive dialogue”. At that point, when the authority makes its selection, the Alcatel Letter is issued and the standstill period should then commence. At the end of that period the contract is signed.

How long is the Standstill Period?

10 to 15 days from the decision to award, depending on the method by which the Alcatel letter is communicated. This is designed to give unsuccessful bidders an opportunity to challenge the award if they believe there has been a breach of the procurement rules.

Who should be sent an Alcatel letter?

Both the successful and unsuccessful “tenderers” and “candidates” in a procurement.. In other words, not only unsuccessful bidders but also any applicant who submitted a “PQQ” (a completed prequalification questionnaire) should receive one.

Full details here